Portsmouth Sailing Club Completes Major Refurbishment Project

Published 21:28 on 14 Apr 2026

Portsmouth Sailing Club has reached a key milestone in its refurbishment programme, following the approval of funding at the PSC General Meeting held on 10 September 2025. At that meeting, members voted in favour of allocating funds for essential structural repairs and the redevelopment of the beer store, gents changing rooms, and toilet facilities.

Contractor Selection Process

The Committee received complete quotations from three separate contractors, including one new contractor who was recommended by a club member. After careful consideration of all the information provided, the Committee appointed PFC Restoration Ltd to undertake the works.

PFC Restoration Ltd was selected based on multiple factors, including price, previous similar projects, and references. The Committee agreed that this contractor is best suited to meet the needs of Portsmouth Sailing Club and to deliver the project to the required standard.

Programme of Works

  • Start date: Monday 9 February 2026
  • Weeks 1-3: The club was completely closed to all members to allow the initial phase of works to be completed safely and efficiently.
  • Weeks 4-5: The club operated in a limited capacity:
  • The ladies facilities were temporarily used as a unisex facility.
  • The Bar and JA Room were available.

These dates were selected after reviewing historical club usage during this period, which indicated it is typically one of the quietest times for organised activities and general member use. Scheduling the works at this time helped to minimise disruption to members while allowing the project to be completed as efficiently as possible.

The clubhouse was reopened on Sunday 1 March at 2:00 pm, operating in a limited capacity.

Project Progress and Completion

Here are a few selected photos of the before, during and after

The project has now been completed and the builders have completed the works. Things ran to schedule and a successful outcome has been achieved,

Usage of the clubhouse has now returned to normal with the new facilities fully available.

Acknowledgements

The Committee would like to thank

PFC Restoration Ltd for the fantastic job they have done. They have been excellent to work with throughout the project.

Thanks are also due to all those members who have helped with various jobs around the clubhouse, contributing to keeping the building to a high standard during and after the refurbishment.